Cypress releases study on Clayton Valley lithium project in Nevada

By Canadian Mining Journal staff / May 21, 2020 / www.northernminer.com / Article Link

With an initial US$493-million investment, Cypress Development's (TSXV: CYP) Clayton Valley lithium project could produce 27,400 tonnes lithium carbonate equivalent (LCE) per year over a 40-year mine life, according to a prefeasibility study (PFS) released this week.

At an 8% discount rate, the project has an after-tax net present value of US$1.1 billion, an internal rate of return of 25.8%, and a payback period of 4.4 years.

"This PFS is a major milestone for Cypress," CEO Bill Willoughby stated in a news release. "These positive results take us closer to our goal of developing a world-class lithium deposit. Cypress's land position and resources afford us the opportunity for a long-life project with low operating costs and potential to be a significant source of lithium for the United States."

An average LCE price of US$9,500 per tonne was used in the study, which projects a low cash cost of US$3,329 per tonne LCE.

Reserves at Clayton Valley are contained in a leachable lithium-bearing claystone. The deposit is large, at surface, and flat-lying, which will allow for a very low strip ratio (0.15:1) and means no drilling or blasting would be necessary to mine the deposit. The study envisions a mining rate of 15,000 tonnes per day.

The project is located next to North America's only lithium brine operation, the Albemarle Silver Peak mine.

Cypress Development's Clayton Valley lithium project in Nevada. Credit: Cypress Lithium.

The lithium in the deposit is amenable to leaching with dilute sulphuric acid leach followed by filtration, solution purification, concentration, and electrolysis to produce lithium hydroxide. Cypress reports that metallurgical leach tests have demonstrated an average of 86.5% extraction of lithium into solution and 126.5 kg/t for acid consumption.

Metallurgical testing indicates low-cost processing can be achieved by leaching with low acid consumption and high lithium recovery. Self-generated power from a 2,500 tonne per day acid plant is also included in the project's costs.

The Vancouver-based junior says testing to recover the lithium from solution has been successful, with the production of a concentrated lithium solution suitable for producing lithium hydroxide.

Before moving to the feasibility and permitting stage, the next step for Cypress will be a pilot plant study, estimated to cost US$6.75 million.

Production figures are based on a probable reserve of 222 million tonnes grading 1,141 parts per million (ppm) lithium for 1.4 million tonnes LCE, calculated at a 900 ppm lithium cut-off grade.

- This article first appeared in our sister publication, Canadian Mining Journal.

Recent News

Silver outperformance driven by weak supply growth

July 29, 2024 / www.canadianminingreport.com

Supply data still points to major silver deficit this year

July 29, 2024 / www.canadianminingreport.com

Canada second most significant player in global mining M&A

July 22, 2024 / www.canadianminingreport.com

Plenty of potential for continued rotation out of tech

July 22, 2024 / www.canadianminingreport.com

Platinum to palladium ratio low, platinum to gold high, versus history

July 15, 2024 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok