Lucapa output rises on Mothae start

By Esmarie Iannucci      / January 16, 2019 / www.miningweekly.com / Article Link

PERTH (miningweekly.com) – Diamond miner Lucapa Diamond Company produced 3 089 ct of diamonds from its Mothae operation, in Lesotho, during the December quarter.

The 1.1-million-tonne treatment plant was commissioned during the December quarter, delivering Lucapa its second operational mine.

Advertisement

Lucapa said on Wednesday that the ramp-up at Mothae continued to progress well, with the plant on target to reach its nameplate capacity of 90 000 t/m by the first quarter of 2019. The targeted treatment rate of 150 t/h has been achieved for extended periods, and was surpassed in December.

At its Lulo operation, in Angola, Lucapa produced 5 070 ct during the December quarter, down 1% on the previous corresponding period due to the processing of gravels from lower-grade areas.

Advertisement

Annual production for the full 2018 was up 3% on 2017, however, to 19 196 ct.

During the quarter under review, the Lulo operation produced 50 special diamonds, bringing the full-year total to 214. The specials recovered during the quarter included three diamonds larger than 50 ct each, with the largest being 75 ct.

Recent News

Bullish bankers and bearish institutions split on gold forecasts

July 01, 2024 / www.canadianminingreport.com

Gold stocks down on flat metal price and mixed equities

July 01, 2024 / www.canadianminingreport.com

Snowline Gold reports Initial Resource Estimate

June 24, 2024 / www.canadianminingreport.com

Inflation subsiding and rate cuts starting internationally

June 24, 2024 / www.canadianminingreport.com

Inflation rebound continues to reverse

June 17, 2024 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok